Carriage House Renovation – Week 10

 

We now have the beginnings of a new third floor underway! The sub-floor has also been laid down for the rear-half of the building. As you can see, things are really moving.

 

Carriage House Renovation – Week 7

 

Progressing forward with the new structural steel! C-joists are going in on the rear half of the second floor, with preparations being made for the new third floor.

 

Carriage House Renovation – Week 5

 

The new steel structure is now going in! As the weeks continue, the GC will replace the old wood joists with steel beams and C-joists, moving from the center of the building moving outwards to keep the masonry walls stable and braced during the process.

 

Carriage House Renovation – Week 2

IMG_1366

 

Demolition has begun! All interior partitions of the existing floors have been removed, leaving behind one large open second floor.

 

Carriage House Renovation – Existing

IMG_3971

 

We’re very happy to say we finally started construction in November on a project that has been in development for more than a year!

 

In essence, this is a gut renovation of a deterioratedĀ carriage house located in a Brooklyn historical district and situated across the street from a very stunning church building. The renovation will bring restoration and balance to the front facade as well as reconfigure the interior for the new family moving in. A roof extension will add some badly needed space and open up to a new roof deck for additional outdoor space.